Kitchen Remodel Order of Work: Steps and Typical Timeline

Updated November 19, 2026

A kitchen remodel follows a fairly fixed sequence because each trade depends on the one before it. Wiring and pipes go in before walls are closed, cabinets go in before countertops can be measured, and countertops go in before the backsplash and the sink connections.

This guide sets out the usual order and typical durations for a full remodel. Actual schedules depend on scope, product lead times, the contractor's workload and local inspection timing. Permit requirements vary by jurisdiction, so confirm them with the local building department.

Typical timeline by phase

PhaseTypical duration
Design, selections and estimates4 to 12 weeks
PermitsA few days to 8 weeks, depending on the jurisdiction and scope
Cabinet and material lead time4 to 16 weeks, running alongside permits
Demolition and any framing changes2 days to 2 weeks
Rough plumbing, electrical and ductwork, with inspections1 to 2 weeks
Insulation, drywall, priming1 to 2 weeks
Flooring2 to 5 days, placement in the sequence depends on the material
Cabinet installation2 to 5 days
Countertop template, fabrication and installation1 to 3 weeks
Backsplash, finish electrical and plumbing, appliances, paint1 to 2 weeks
Final inspection and punch listA few days to 2 weeks

For a full remodel without structural changes, the construction phase commonly lasts 6 to 12 weeks. The planning and ordering period before it is often just as long.

Planning, selections and ordering

Most delays begin before construction starts. The design should be complete, and the following chosen, before demolition is scheduled:

  • Cabinet layout, door style and finish, with a signed order
  • Appliance models, with installation guides given to the designer and electrician
  • Sink and faucet models
  • Countertop material
  • Flooring, backsplash tile and grout
  • Lighting fixtures and the positions of switches and outlets
  • Hardware and paint colors

Demolition is best scheduled only after the cabinet delivery date is confirmed. Removing a working kitchen and then waiting weeks for cabinets is the most common avoidable hardship in a remodel. Permit applications are usually submitted during this period by the contractor.

Demolition and structural work

The room is emptied, floors in adjoining areas are protected, and dust barriers are set up. Water, gas and electrical circuits to the kitchen are shut off and capped. Cabinets, countertops, appliances, flooring and damaged drywall are removed.

In homes built before 1978, painted surfaces may contain lead, and federal rules require contractors who disturb them to be certified and to follow lead-safe practices. Older flooring, adhesives, and some wall and ceiling materials can contain asbestos and should be tested before removal.

Any framing changes follow: removing or moving walls, resizing window and door openings, and adding blocking in walls for cabinets and heavy fixtures. Removing a bearing wall requires an engineered design and a permit. Hidden conditions found at this stage, such as water damage or outdated wiring, are dealt with before work continues.

Rough-in and inspections

Rough-in is the installation of everything that will be hidden inside walls, floors and ceilings.

  1. Plumbing: drain, vent and supply lines for the sink, dishwasher, refrigerator water line and any pot filler or island sink. Gas piping for a range or cooktop.
  2. Mechanical: the range hood duct to the exterior and any changes to heating and cooling ducts.
  3. Electrical: new circuits, boxes for receptacles, switches and lights, and wiring for appliances and under-cabinet lighting.
  4. Inspections: the plumbing, mechanical and electrical rough-in must be inspected and approved before the walls are closed.

This is the last point at which locations can be changed easily. It is worth walking the room with the plans before inspection to confirm outlet heights, light positions, the sink centerline and the hood duct location against the cabinet drawings.

Walls, flooring and cabinet installation

After inspections, insulation is installed in exterior walls, drywall is hung, taped and sanded, and the walls and ceiling are primed. Many contractors apply the first coat of paint at this stage and the final coat near the end.

Flooring comes before or after cabinets depending on the type. Tile and fastened hardwood are often laid first. Floating floors are laid after the cabinets. In either case the finished floor is protected with a covering for the rest of the job.

Cabinets are installed level and plumb, starting from the high point of the floor, and fastened to the wall framing and to each other. Wall cabinets are commonly hung first so the installers can work without reaching over the base cabinets. Panels, fillers and crown molding follow. Appliances should be on site or their dimensions confirmed, so openings can be checked.

Countertops, backsplash and finish work

Stone, quartz and solid surface countertops are measured, or templated, only after the base cabinets are fully installed. The sink, faucet and cooktop must be on site for the template. Fabrication usually takes one to three weeks, which is the main waiting period late in the project. A temporary plywood top and sink can sometimes be arranged in the meantime.

  1. Countertop installation, including the undermount sink.
  2. Backsplash tile, grout and sealant.
  3. Finish plumbing: faucet, disposal, dishwasher and water lines.
  4. Finish electrical: receptacles, switches, light fixtures and under-cabinet lights.
  5. Appliance installation and hood connection.
  6. Cabinet hardware, door and drawer adjustment, touch-up.
  7. Final paint, flooring trim and cleaning.
  8. Final inspections, then the punch list of small items to correct.

Common scheduling mistakes

  • Starting demolition before cabinets have a confirmed delivery date
  • Choosing appliances, the sink or the faucet after rough-in, which forces rework
  • Expecting countertops immediately after the cabinets are set
  • Closing walls before the rough-in inspection
  • Making changes during construction without a written change order and a revised schedule
  • Not inspecting cabinets and materials for damage when they are delivered
  • Leaving no slack for back-ordered items or failed inspections
  • Making the final payment before the punch list is complete

Frequently asked questions

How long does a kitchen remodel take?

The construction phase of a full remodel usually takes 6 to 12 weeks without structural changes. Design, permits and cabinet lead time before construction often add 2 to 4 months. A cosmetic update can take 1 to 3 weeks.

Are cabinets or flooring installed first?

It depends on the flooring. Tile and nailed or glued hardwood are often installed before cabinets. Floating floors such as click vinyl plank and laminate are installed after cabinets so they are not pinned in place.

When are countertops measured?

After the base cabinets are installed, level and fastened. Stone and quartz are then fabricated from that template, which usually takes one to three weeks before installation.

What inspections does a kitchen remodel need?

A permitted remodel typically has rough-in inspections for electrical, plumbing and mechanical work before walls are closed, and a final inspection at the end. Structural changes add a framing inspection. The local building department sets the exact list.

How long will the kitchen be unusable?

From demolition until the countertops and sink are installed, which is commonly 5 to 10 weeks in a full remodel. Setting up a temporary kitchen elsewhere in the house makes this period much easier.